Harrisburg Water Reclamation Facility

WATCH THE VIDEO BELOW TO SEE THE PROGRESS BEING MADE

SITE UPDATES (AS OF JANUARY 2021)

General Site Work

  • Mass Grading – COMPLETE

  • Site Utilities – In Progress

  • General Concrete – Spring 2021

  • Final Grading – Fall 2021

Headworks Building Area

  • Excavation - COMPLETE

  • Building Footings & Walls - COMPLETE

  • Building Roof – In Progress

  • Interior Finishing – Spring 2021

  • Process Piping – Spring 2021

  • Mechanical & Electrical – Summer 2021

Biological Treatment Basins

  • Excavation - COMPLETE

  • Concrete Footing & Walls – COMPLETE

  • Concrete Finishing & Final Grading – In Progress

  • Sludge Pump Building – In Progress

  • Process Piping – Spring 2021

  • Mechanical & Electrical – Summer 2021


Biosolids Storage Area

  • Excavation – Spring 2021

  • Concrete – Spring 2021

Final Treatment/Operations Building Area

  • Excavation – COMPLETE

  • Pump Station Concrete Footing & Walls - COMPLETE

  • Building Footings & Walls - COMPLETE

  • Internal Building Walls – In Progress

  • Building Roof – In Progress

  • Process Piping – In Progress

  • UV Structure – Summer 2021

  • Mechanical & Electrical – Spring 2021

  • Interior Workspace Finishing – Summer 2021

CLICK THROUGH THE IMAGES BELOW THE SEE THE PROJECTS PROGRESS